Providing a FREE U.S. Army Board Study Guide and resources for Army Soldier and NCO Boards and SGT / SSG Promotion Boards since 1999
  Common Tasks SMCT
Online Since 1999  
Please recommend our FREE Army Study Guide to another Soldier.
 
Browse More In:
 
 Navigation
 
 Sub Navigation
 
Civilian Job Center
Ready to transition? Find a post-military career today [Go]
 
FREE Audio Version
of our Study Guide. Choose the sections you want to study [Go]

Download & print
the most recent full version of the FREE ArmyStudyGuide.com Study Guide [Go]
 
Enter your email address to receive the Military Network newsletter.

Thank you!

You are now subscribed to the ArmyStudyGuide Newsletter. Expect your first issue shortly!

 
You are here: home > common tasks smct > skill levels 2-4 > 052-195-3066 (sl3) - direct construction of nonexplosive obstacles

052-195-3066 (SL3) - Direct Construction of Nonexplosive Obstacles
Standards: Directed the construction of obstacles that were tied to existing or reinforced obstacles to block, channel, or delay the enemy according to the mission brief or intent.

Posted Monday, October 10, 2005

Conditions: Given a mission directive, logistical support for the type of nonexplosive obstacle, squad personnel, organic equipment, and FM 5-34.

Standards: Directed the construction of obstacles that were tied to existing or reinforced obstacles to block, channel, or delay the enemy according to the mission brief or intent.

Performance Steps

1.   Analyze mission requirements using the mission, enemy, terrain, troops, time available, and civilian considerations (METT-TC) factors.  Consider the following—

a. Manpower available.

b. Material available.

c. Time available.

d. Type of transportation.

e. Site selection (take advantage of existing obstacles).

f.  Type of obstacle to be constructed.

2.   Direct the construction of wire obstacles.

Note. When using U-shaped pickets to construct obstacles, ensure the U faces the enemy.

a. Direct the construction of a double-apron 4- and 2-pace fence.  Ensure—

(1)  The fence centerline is laid.

(2)  The long pickets are spaced at 3-meter (4-pace) intervals.

(3)  The anchor pickets are spaced at 1.5-meter (2-pace) intervals each way from the centerline and midway between the long pickets.

(4)  All 12 wires are installed.  Ensure work is done from the enemy side to the friendly side (figure 052-195-3066-1).


Figure 052-195-3066-1.  Double-Apron Fence

Note.  Ensure the soldier is not cut off between the enemy and the fence.

(5)  The wire is tied at the beginning and end of each roll of barbed wire, as a minimum.

(6)  The wires are properly secured and tight.

b. Direct the construction of a triple-standard concertina fence.

(1)  Ensure work is done from the enemy side to the friendly side.

(2)  Direct the installation of an anchor picket (short picket) at each end of the front and back row (2 paces).

(3)  Ensure long pickets are spaced at 3.8-meter (5-pace) intervals (stagger the back row) (figure 052-195-3066-2).


Figure 052-195-3066-2.  Triple-Standard Concertina Fence

Note. Install the pickets in such a manner that the lower notch of the long picket is 4 inches above the ground.

(4)  Direct the installation of concertina wire.  Ensure—

(a)   A roll of concertina is placed at the third picket in the front row and at every fourth picket thereafter (figure 052-195-3066-3).


Figure 052-195-3066-3.  Install Concertina and Horizontal Wire


(b)   The bottom row (concertina wire) is secured with the horizontal wire (barbed wire) (figure 052-195-3066-4).


Figure 052-195-3066-4.  Join Concertina Wire

(c)   The back row (friendly side) is begun once the first team has cleared the head of the fence.

(5)  Direct the installation of the remaining row of concertina wire on top of the first two rows and fasten it securely.

(6)  Ensure the concertina wire is properly tied and all horizontal wire is properly installed.

c. Direct the construction of a four-strand cattle fence.

(1)  Ensure an anchor picket (short picket) is installed at each end of the fence.

(2)  Ensure the long pickets are installed 3 meters apart (figure 052-195-3066-5).


Figure 052-195-3066-5.  Four-Strand Cattle Fence

(3)  Direct the installation of the barbed wire.  Ensure—

(a)   The reel of barbed wire is rolled out.  Ensure that a row of barbed wire is used per strand.

(b)   The wire is tied from the bottom strand and that it is worked upward to the top strand.

(4)  Ensure the wire is taut and tied correctly.

d. Direct the construction of a knife rest.

(1)  Ensure that a knife rest is prepared 3 to 5 meters long (figure 052-195-3066-6).  Ensure—


Figure 052-195-3066-6.  Knife Rest

(a)   The end poles (1.2 meters in height and width) are lashed to form two Xs.

(b)   The center pole is lashed to the two Xs.

(c)   Barbed wire is used to complete the knife rest.

(2)  Ensure the knife rest is secured to the ground.

e. Direct the construction of an 11-row obstacle out of concertina wire.

(1)  Ensure long pickets are installed at 3.8-meter (5-pace) intervals for 11 rows (figure 052-195-3066-7).

 


Figure 052-195-3066-7. Eleven-Row Obstacle

(2)  Direct the placement of concertina wire over the long pickets.

(3)  Ensure the horizontal wire (barbed wire) is anchored to the anchor stakes 1.5 meters (2 paces) from each end of the concertina rows.

(4)  Ensure the horizontal wire is secured over the concertina wire.

(5)  Ensure that a log 20 centimeters in diameter is placed between the fifth and sixth row.

(6)  Ensure the obstacle is no less than 10 meters deep.

3.   Direct the construction of log obstacles.

Note. When constructing a log crib, use only logs with a 20-centimeter diameter minimum.

a. Direct the construction of a triangular log crib (figure 052-195-3066-8).  Ensure—


Figure 052-195-3066-8.  Triangular Log Crib

 

(1)  The vertical postholes are marked and dug 1.5 meters deep.  Ensure one corner of the log crib is facing toward the enemy and four 3-meter posts are used per wall.

(2)  The 12 horizontal logs (four per wall) are cut to roadway width.

(3)  The vertical logs are emplaced and tamped into place.

(4)  The horizontal logs are emplaced and posts are lashed together with wire.

(5)  The interior of the crib is filled with earth material taken from the enemy side of the obstacle.

b. Direct the construction of a rectangular log crib (figure 052-195-3066-9 and table 052-195-3066-1).  Ensure—

 


Figure 052-195-3066-9.  Rectangular Log Crib

Table 052-195-3066-1. Post Requirements
(Post Opposing/Offset Post Designs)

Road Width (m)

 

1.8

2.1 to 3.6

3.9 to 5.4

5.8 to 7.3

 

8

12

16

20

 

2

3

4

5

 

4

6

8

10

 

Note. A rectangular log crib can be emplaced with the post opposing design or the offset-post design.

(1)  The vertical postholes are dug and marked 1.5 meters deep.  Use table 052-195-3066-1 for post requirements.

(2)  The horizontal logs (four per wall) are cut to the roadway width.

(3)  The vertical logs are emplaced 1.8 meters apart and tamped into place.

(4)  The horizontal logs are emplaced and posts, logs, and braces are lashed with wire.