Use to report results of route reconnaissance. Reference: FM 5-34, FM 17-95, and FM 17-98.

LINE 1 -- DATE AND TIME______________________________(DTG)

LINE 2 -- UNIT________________________________________(Unit Making Report)

LINE 3 -- RECON TIME_________________________________(DTG Start and Completion of Recon)

LINE 4 -- RECOND ROUTE______________________________(Route Reconned)

LINE 5 -- TRAFFICABILITY _____________________________(Trafficability of Route)

LINE 6 -- BUILT-UP AREAS _____________________________(Built-up Areas Along Route/Grid Coordinates)

LINE 7 -- LATERAL ROUTES ____________________________(Lateral Routes Reconned/ Results)

LINE 8 -- BRIDGE CLASS _______________________________(Bridge Classification Report/Grid Coordinates)

LINE 9 -- FORDS ______________________________________(Fords and Crossings Site/ Grid Coordinates)

LINE 10 -- BYPASSES__________________________________(Overpasses, Underpasses, Culverts/Grid Coordinates)

LINE 11 -- OBSTACLES_________________________________(UTM or Six-Digit Grid Coordinate With MGRS Grid Zone Designator of All Obstacles, Minefields, Contaminated Areas)

LINE 12 -- ENEMY_____________________________________(Enemy Activity That Can Influence Route/Grid Coordinates)

LINE 13 -- NARRATIVE_________________________________(Free Text for Additional Information Required for Clarification of Report)

LINE 14 -- AUTHENTICATION___________________________(Report Authentication)